PECO will be replacing the existing natural gas equipment to enhance service in your neighborhood. This includes installing new underground pipe, which is more durable, enhances safety and improves service reliability.
About the Project:
- Work is expected to begin 12/9/24, Monday through Friday from 7 a.m. – 3 p.m, in the area of Ellis Road between Easton Road and Grant Avenue, and Grant Avenue from Ellis Road to Crown Street.
- The project is expected to be completed in February 2025.
- This work will be performed by Riggs Distler, a qualified PECO contractor. If you have any questions or to schedule an appointment, please contact Steve Resh of Riggs Distler at 609-519-9794.
- If you are not the owner of the building, please forward this written notice to the owner of the building.
If you have any other questions about this work and/or would like to provide any supplemental information, please call PECO Work Inquiries (610) 832-6420 or email GasWorkInquiries@exeloncorp.com.